Ensuring clean, fresh tap water continues to flow to our customers taps 24 hours a day, seven days a week is one of our top priorities. That’s why between 2020 and 2025 we’re investing more than £489 million upgrading old water mains, installing new pipelines, improving our water treatment works and maintaining our reservoirs.
Some of this improvement work takes place on our own sites, however a lot more besides happens along roads in public areas. Here are just a few examples of the vital work we are undertaking across our supply area.
Butler Water Treatment Works, Maidstone
Work continues at pace on our brand-new, state-of-the-art water treatment works near Maidstone.
The new £39 million facility will provide up to 20 million litres of treated drinking water a day to the area, once built, representing a key investment for Kent and a vital part of our plans to ensure we can continue to supply the area with tap water as the population grows.
In addition to new boreholes, we will also make use of the existing boreholes, pipework and storage tank already at the site. By upgrading infrastructure already in place, we are ensuring these existing facilities reach drinking water quality standards, reduce construction costs and reduce the carbon footprint of the project.
With the main structure erected we are on track for the site to be fully operational by March 2025.